How long will my load be locked out if it causes an overload when using a SACM or Load Manager?

When a Generac Load Manager or Integrated Smart Air Conditioning Module (SACM) enables a managed load that overloads the generator within 15 seconds, that load is locked out for 30 minutes, then reattempted. There’s no permanent lockout; the timer resets when utility power returns or the generator is shut down. If an AC won’t start, avoid changing load manager settings and contact a dealer—this guidance applies to transfer switches with a SACM or load manager—so managed loads operate safely and reliably (search: “SACM lockout time,” “load manager lockout,” “AC not coming on”).

Title
How long will my load be locked out if it causes an overload when using a SACM or Load Manager?
URL Name
How-Long-Will-My-Load-Be-Locked-Out-if-It-Causes-an-Overload-When-Using-a-SACM-or-SMM

Public Answer
Was this article helpful?